Silvertown Tunnel, London

17/06/2026

Key Statistics:

Contract Value: circa £1.3 Million
Project Duration: 2024 - 2024
Scope: 25 high-performance Stainless Steel Tunnel Doorsets

Project Overview

  • The Silvertown Tunnel is a new 1.4km twin-bore road tunnel beneath the Thames, linking Greenwich Peninsula with Silvertown.
  • Booth Industries were contracted to design, manufacture and install 15 cross passage emergency escape doors and 10 plant room doors.
  • Our extensive tunnel experience — including HS2 and other major infrastructure schemes — positioned Booth as the trusted partner for this project.

 

 

What were the project complexities?

  • Emergency escape doors designed to BD78/99, providing up to 2 hours of fire protection, safe evacuation routes for the public, and assured firefighter access.
  • Doors required to withstand constant ±3kPa pressure cycles from the “piston effect” of traffic, while incorporating vision panels for safety awareness.
  • Plant room doors required EI120 fire integrity and insulation alongside pressure fatigue resistance.
  • Booth redesigned its proven road tunnel door system and substantiated performance using: Small-scale destructive testing Advanced Finite Element Analysis
  • Assurance provided for a 35-year design life.

What did we overcome?

  • Confined and heavily programme-driven tunnel environments demanded absolute precision.
  • Any installation delay risked major knock-on impacts.
  • Through early coordination with architects and contractors, we ensured: Structural openings were built to precise tolerances. Designs aligned with manufacturing and fire assurance requirements. Installation risks were removed before work began.

What did Booth achieve?

  • Delivered and installed all doorsets two months ahead of schedule.
  • Ensured the Silvertown Tunnel opened on time in April 2025.

Our professionalism, problem-solving mindset and unwavering focus on quality were praised by the Joint Venture project team: